Project Name: Phase 2B
Phase Type: 2B Modernization
Campus: 09 - Valhalla
Phase Status: Complete
Percent Complete: 100 %
Scope of Project: Replacement of 22 air handler units, electrical upgrade, and site utilities
Budget: Project Complete
Schedule: Project Complete
Architect: Platt Whitelaw
Construction Manager: C.W. Driver
Project Manager: Janea Quirk
Prop: Prop H