Project Name: Modernize Buildings 400/500/700
Phase Type: 2011
Campus: 08 - Santana
Phase Status: Construction
Percent Complete: 25 %
Scope of Project: Existing Building is 14,080 sq. ft. Building will be modernized to provide three special education clusters to campus for students with significant disabilities. The special educational classrooms have specific requirements to include a special hygiene area with washer and dryer, and a life skills lab with a dedicated sink.
Budget: Going Well
Schedule: Going Well
Architect: Harley Ellis Devereaux
Construction Manager: Balfour Beatty
Project Manager: Dena Johnson
Prop: Prop U