Grossmont Union High School District

Project Name: Gymnasium Restroom ADA Remodel
Phase Type: 2B Modernization
Campus: 08 - Santana
Phase Status: Complete
Percent Complete: 100 %
Scope of Project: Perform all required underground infrastructure (electrical, gas, water, sanitary sewer, drainage, communications, fire alarm and data) work. Abate all hazardous materials within the restroom facility; address the removal of barriers consistent with the ADA transition plan.
Budget: Project Complete
Schedule: Project Complete
Architect: Harley Ellis Devereaux
Construction Manager: Erickson Hall
Project Manager: Janea Quirk
Prop: Prop H