Grossmont Union High School District

Project Name: 2015 Summer Sprint Project
Phase Type: 2015
Campus: 07 - Monte Vista
Phase Status: Design
Percent Complete: 30 %
Scope of Project: Modernization of 700 bldg is based on future PAC/MPR scope. Modernization includes upgrades to lighting retro-fit for energy savings, ADA compliant doors, restrooms and bleachers, hearing assistance devices and other upgrades. Modernization of the facility to District standards with CTE components. Further needs assessment will take place before final scope is determined. Modernization of the facility to District standards. Further needs assessment will take place before final scope is determined.
Budget: Going Well
Schedule: Going Well
Architect: Harley Ellis Devereaux
Construction Manager: TBD
Project Manager: Scott Wilkins
Prop: Prop U