Grossmont Union High School District

Project Name: Phase 3A New Science Building
Phase Type: 3A New Building
Campus: 
Phase Status: Complete
Percent Complete: 100 %
Scope of Project: The scope of the New Science Building Project (3A) encompasses designing a two-story (17,033 GSF) science classroom building. The program consists of ten (10) classrooms (4 Chemistry; 4 Biology; 2 Physics) and New Restrooms. The building will be designed to the current District Standards as to performance capabilities, and per Education Code and building codes (ADA compliance, Fire Life Safety, Structural). Site Preparation includes the demolition and removal of four (4) relocatable classroom buildings. The underground utility infrastructure (wet & dry) utilities will removed, rerouted, installed (as required or requested) consistent with the underground utilities infrastructure plan.
Budget: Project Complete
Schedule: Project Complete
Architect: Harley Ellis Devereaux
Construction Manager: Turner Construction
Project Manager: Debbie Murray
Prop: Prop H