Grossmont Union High School District

Project Name: Phase 3A New Science Building
Phase Type: 3A New Building
Campus: 06 - Granite Hills
Phase Status: Complete
Percent Complete: 100 %
Scope of Project: The scope of the New Science Building Project (3A) encompasses designing a one-story (14,033 GSF) science classroom building. The program consists of ten (8) classrooms (2 Chemistry; 4 Biology; 2 Physics) and New Restrooms. The building will be designed to the current District Standards as to performance capabilities, and per Education Code and building codes (ADA compliance, Fire Life Safety, Structural). Site Preparation work consists of the relocation of one classroom; add 3 relocatable classrooms; demolition of 2 buildings, slabs & foundations. The underground utility infrastructure (wet & dry) utilities will removed, rerouted, installed (as required or requested) consistent with the underground utilities infrastructure plan
Budget: Project Complete
Schedule: Project Complete
Architect: HMC/RRC
Construction Manager: Erickson Hall
Project Manager: Dena Johnson
Prop: Prop H