Grossmont Union High School District

Proposed Alpine school site plan
Prop U Performance Measures

Prop U Performance Measures iconProp U Performance Measurestitle

New High School Site Improvements/Utilities
  • Phase: Design
  • Budget: On Target
  • Schedule: On Target
  • Phase Type: 2017
  • Percent Complete: 95%
 
New High School Buildings
  • Phase: Design
  • Budget: On Target
  • Schedule: On Target
  • Phase Type: 2017
  • Percent Complete: 95%
 
Site Acquisition
  • Phase: Complete
  • Budget: Complete
  • Schedule: Complete
  • Phase Type: New School
  • Percent Complete:100%